Construction Update
The BOB
July 2026
About the Project
The Bob is a 7.2-acre residential development located at 703 Columbia Park Trail, featuring a total of 192 thoughtfully designed homes with an average size of 910 square feet. The community will offer a mix of studio, one-bedroom, and two-bedroom layouts, along with a central clubhouse that includes a leasing office, fitness room, and multi-purpose community space. Residents will enjoy a range of resort-style amenities, including a pool and spa, BBQ area, outdoor lounge, and dog park. The project will provide 299 parking stalls, including seven garage structures with 33 enclosed spaces.
Construction will be delivered in three phases to allow for staggered occupancy, with Phase 1 (72 units and the clubhouse) scheduled for completion on November 27, 2026, Phase 2 (48 units) on February 1, 2027, and Phase 3 (72 units) on May 21, 2027.
Construction Update – July 2026
Construction continues to make steady progress at The BOB Apartments, with work advancing across residential buildings, community amenities, garages, and site improvements. As exterior work nears completion, crews are shifting their focus toward interior finishes and final site infrastructure.
What’s Happening This Month
- Interior finishes are progressing, including cabinet installation, painting, and mechanical, electrical, and plumbing (MEP) work across multiple residential buildings.
- Exterior siding is now complete on all apartment buildings and garages.
- Work continues on the clubhouse, amenity spaces, and mechanical rooms with insulation and drywall installation.
- Site improvements are nearing completion, including curb and gutter installation, roadway preparation, and off-site sidewalk work.
- Asphalt paving is scheduled to begin later this month.
What Neighbors May Notice
Neighbors may continue to see regular construction activity during normal working hours, including:
- Interior finishing work throughout the buildings
- Site grading and roadway preparation
- Construction vehicles entering and exiting the site
- Equipment movement throughout the property
- Asphalt paving activities beginning later this month
Traffic & Safety Reminder
Construction access from Columbia Park Trail continues to have minimal traffic impacts; however, the roadway remains busy and narrow in some areas. Beginning the week of July 20, paving operations will take place onsite, and neighbors may notice increased construction traffic associated with these activities.
We kindly ask drivers and pedestrians to remain alert for construction vehicles entering and exiting the site and to allow space for safe roadway access.
We appreciate the community’s continued patience and support as construction progresses.
We apologize for any inconveniences throughout the construction process. The safety of all employees, neighbors and the general public is our number one priority. Please be aware of changing conditions in the public right-of-way as sidewalk and street conditions are ever changing. Heavy equipment is entering and exiting the jobsite regularly. Please be aware of your surroundings and help us keep this project safe and free of injury.
Thank you.
Hours of Operation
Monday–Friday: 7:00 AM – 7:00 PM
Saturday): 7:00 AM – 5:00 PM
Contact Us
Ben Robles
Project Manager
(509) 844-1569
Daniel Engel
Project Engineer
(509) 820-8547
Rudy Lopez
Superintendent
(858) 568-2229