Construction Update

Gridline Apartments

December 2023

About the Project

The Gridline Apartments will consist of two buildings — a north and west building. The North Building will be 161,601 s.f. with 2,850 s.f. of common amenity space and 129 units. Community amenities will include a fitness room, rooftop club room, and a roof deck with incredible skyline views, vegetated roof areas, custom BBQ table, and outdoor fire tables. The North Building also offers multiple bike storage rooms, a secured parcel room, a tranquil courtyard, and roughly 1,256 s.f. of co-working space to accommodate the teleworking lifestyles. The West Building (31,261 s.f., 49 units) will include two secured bike storage rooms, secured parcel room, and a roof deck with sweeping view, BBQ, fire table and vegetated roof areas.

Scheduled completion date is Q4 2023

Scheduled Work:

The interiors of the North Building are taking their final shape! All the corridors have been equipped with light fixtures, paint, and P-Lam panels at unit entries and elevator fronts. The corridor and elevator lobby flooring installation on typical levels is also underway. We are currently addressing loose ends level by level to pull things together and are initiating the punch list process on Level 7 this week! Other trades are also making rapid progress including the installation of appliances, plumbing trim, shower doors, and bedroom carpet installation on Levels 1 and 2. Unit finishes are nearing completion on most levels and the initial cleaning phase is already underway. Installation of the decorative box baffle ceiling in the main double-height lobby is complete, bringing the lobby to its final form. 

On the exteriors, the man lift area on the east elevation is now enclosed with windows being installed, masonry work in progress, and concurrent drywall installation ongoing on the inside at this location.  

Planned Street Interruptions

Seattle City Light is working inside our building to get us energized, and we also have exterior improvement work underway on Harvard Avenue that may cause some lane narrowing on this street. We request neighbors to please utilize the leads from the construction flaggers and stop or slow down when notified to maintain overall safety.

We apologize for any inconveniences throughout the construction process. The safety of all employees, neighbors and the general public is our number one priority. Please be aware of changing conditions in the public right-of-way as sidewalk and street conditions are ever changing. Heavy equipment is entering and exiting the jobsite regularly. Please be aware of your surroundings and help us keep this project safe and free of injury.

Thank you.

Hours of Operation

7:00am – 6:00pm, Monday through Friday & non-legal holidays

9:00am – 6:00pm, Saturdays and legal holidays

No work on Sundays unless it’s an emergency.

Work outside of permitted hours (such as specified holidays) may occur on a case by case basis as approved by Building Services Department.

Stay Notified About This Project!

    Contact Us

    Danielle Locklar

    Senior

    Project Manager

    831.277.8680

    Christian Dobbins

    Project Engineer

    503.310.6447

    Jyoti Bhadrashetti

    Project Engineer

    415.712.9789

    James Wilkins

    Project

    Superintendent

    425.772.0107

    Scroll to Top
    Scroll to Top