Crews are now complete with all residential drywall work. Common area drywall will continue through May. Exterior cladding at the roof level is wrapping up and we are working on
The Astro continues to move along at a good pace and the team is working hard to keep the momentum going. On the ground level there are a few ‘feature’
Workers are currently forming and pouring structural footings, walls, and columns at the SW and SE quadrants in advance of our first SOG pour on 4/16. The first shortcrete perimeter
This month we will be installing gypsum wall board in the last of the L9 and ground floor Townhouse units. Finish paint is complete on levels three and four, and
The exterior envelope work is wrapping up and site work is in progress. Storefront glazing systems will be complete by the end of April. The interior mechanical, electrical, and plumbing